A bowtie shows how a hazard could lead to an accident, and which barriers stand in the way. In Centrik, those barriers are risk controls: reusable records that you define once and apply wherever they protect you. Two signals then tell you whether each control can be trusted. Health comes from the documents, audits and training records that keep the control in place. Effectiveness comes from safety reports that record whether the control held when it was tested.
This article explains the concepts and how they fit together. The articles listed at the end give the step-by-step instructions.
Before you start
| Requirement | Detail |
|---|---|
| Modules | Risk Controls must be enabled. Bowtie assessments, escalation factors, consequence templates and control assessment also need the Bowtie risk methodology feature. Contact your Account Manager to enable them. |
| Access rights | Risk Viewer can view controls, control sets and templates. Risk Manager can create and edit them. Anyone who can edit a risk assessment can apply controls to it. |
| Terminology | Labels such as "Risk Control", "Control Set" and "Hazard" can be renamed for your organisation. The screens you see may use different words from this guide. |
Key concepts
The bowtie
| Concept | Definition |
|---|---|
| Hazard | The risk assessment itself. Its name appears at the centre of the bowtie, for example "Runway excursion". |
| Top event | The moment control is lost, for example "Aircraft departs the paved runway surface during landing". You record it on the assessment so everyone reads the bowtie the same way. |
| Threat | A cause that could lead to the top event, such as "Unstabilised approach continued to landing". Each row in the assessment's Hazards Summary is a threat. |
| Consequence | An outcome that could follow the top event, such as "Post-crash fire". Each consequence belongs to a threat and carries its own 5×5 risk score. |
| Preventive control | A risk control applied to a threat. It stops the threat reaching the top event. |
| Recovery control | A risk control applied to a consequence. It limits the outcome once the top event has happened. |
| Escalation factor | A condition that weakens a control, such as crew fatigue weakening a go-around policy. You can attach further controls to the factor to defend against it. |
| Consequence template | A standard set of consequences, each with a Main Impact and default recovery controls, that you can apply to many threats in one step. |
Risk controls
| Concept | Definition |
|---|---|
| Risk control | A barrier your organisation relies on, such as "Stabilised approach criteria and mandatory go-around policy". It has a number, name, owner, description and the risk subsystems where it may be used. |
| Managed control | A control kept in the central list so it can be reused across many assessments. Health and effectiveness build up across every use. |
| Unmanaged control | A one-off control that exists only where it was created. A Risk Manager can convert it to managed later. |
| Control set | A folder for grouping controls, for example "Flight Operations Procedures". A set shows the worst health and effectiveness of the controls inside it. |
| Control application | One use of a control, for example RC-01 applied to the threat "Unstabilised approach". Each application has its own description of use, control context, comments and actions. |
| Control context | Whether the control is in place. Current means it is implemented now. Planned means you intend to implement it. Inherent means it sits outside your control, such as an airport's arresting system. |
| Health monitor | A record that shows the control is being maintained, such as the operations manual that defines it, the audit checklist that checks it, or the qualification that trains crews on it. |
Health and effectiveness
These two signals answer different questions, and a control needs both to be trusted.
| Health | Effectiveness | |
|---|---|---|
| Question | Is the control being maintained? | Did the control work when it was tested? |
| Source | Health monitors: documents, audits, checklists, training and qualifications | Control assessments on safety reports |
| Type of indicator | Leading | Lagging |
| Values | Healthy, Under Stress, Degraded, Critical, Not Monitored | Effective, Concerns, Ineffective, Untested |
| Where to set it up | Health Monitors | Control Assessment for Effectiveness |
For example, RC-01 can show Degraded health because one line-check qualification has expired, and Ineffective effectiveness because a recent report recorded the policy failing. Both statuses appear wherever the control is shown: the control list, the threat page and the bowtie.
Bowtie and Hazards and Consequences compared
Centrik offers three assessment methodologies. Bowtie and Hazards and Consequences use the same records underneath, so you can switch an assessment between them.
| Hazards and Consequences | Bowtie | SIRA (ICAO) | |
|---|---|---|---|
| Structure | A list of hazards, each with consequences | A hazard (the assessment) with threats, a top event and consequences | A single safety issue scored on the ICAO method |
| Risk scoring | 5×5 per consequence, before and after action | The same 5×5 per consequence | SIRA scoring |
| Risk controls | Applied to consequences | Preventive on threats, recovery on consequences, escalation controls on escalation factors | Applied to the issue |
| Diagram | None | Interactive bowtie with health and effectiveness on every control | None |
| Consequence templates | Not available | Available | Not available |
| Switch methodology | To Bowtie | To Hazards and Consequences | Cannot be switched |
Here is the same runway excursion risk in both forms. In Hazards and Consequences, each hazard row holds consequences and their controls on one page:
In a Bowtie assessment, each row is a threat. The threat page adds a Preventive Risk Controls panel above the consequences:
Switching methodology changes only how the assessment is presented. No data is converted or lost. A Risk Manager can switch from the assessment's detail page using Switch Methodology.
Articles in this guide
| Article | What it covers |
|---|---|
| Configuring Risk Controls and Control Sets | Creating control sets and controls, managed and unmanaged controls, archiving |
| Health Monitors | Connecting documents, audits and training to controls, reading health, critical-path monitors |
| Consequence Templates | Building templates, default recovery controls, applying and updating them |
| Creating a Bowtie Risk Assessment | Top event, threats, controls, consequences, escalation factors, scoring, viewing the bowtie |
| Control Assessment for Effectiveness | Assessing controls on safety reports and how effectiveness is calculated |
Related articles: Risk Module (Overview), Creating a Risk Assessment (Evaluation Phase), SIRA - Safety Issue Risk Assessment.